OneMine Platform Modernization

Project Plan

Oct 1, 2026 kickoff through the Jun 2027 grant window

Overview

Six workstreams across four milestones. Select a milestone to see the work tied to it.

Oct2026
Nov
Dec
Jan2027
Feb
Mar
Apr
May
Jun
M1
M2
M3
M4
Data FoundationOct 2026 – Feb 2027
Ingestion PipelineDec 2026 – Apr 2027
Solr / SearchJan 2027 – May 2027
Alpha Research Library (Data)Apr 2027 – May 2027
UX & AccessibilityMar 2027 – May 2027
Testing & LaunchApr 2027 – Jun 2027

Markers show each milestone’s due date. Work after the grant window (FY28) is on its own tab.